A set of drawings can
be consented, coordinated and technically correct.
That does not
automatically mean the project will be easy to build.
For developers and
project managers, buildability is the point where design meets the physical
realities of construction.
When engaging a
commercial construction company in Waikato, early practical input can help
identify labour-intensive details, sequencing problems and trade interfaces
before they affect the programme.
Buildability is not
about contractors overriding designers.
It is about using
construction experience earlier.
Why a Commercial
Construction Company Waikato Reviews Buildability
Design consultants
view a project through their professional discipline.
Architects focus on
design and architectural coordination.
Engineers focus on
structural performance.
Fire engineers focus
on fire design.
Services consultants
focus on mechanical, electrical and hydraulic requirements.
Each discipline is
necessary.
The construction team
sees another issue.
How do we physically
build it?
That question can
expose problems that are difficult to see in a design meeting.
A Simple Detail May
Be Difficult on Site
Consider a wall head.
On a drawing, it may
be represented by several lines and a reference to a standard detail.
On site, the
contractor may need to work around ductwork, cable trays, pipework and
structural steel.
There may be limited
fixing access.
The wall may require a
deflection detail.
It may also require an
acoustic or fire-rated construction.
Several trades may
need access to the same 300 mm area.
The drawing is not
necessarily wrong.
The sequence is the
problem.
A buildability review
asks whether the work can be installed in a sensible order.
The Best Time to
Fix a Construction Problem
There are three basic
opportunities to solve a problem.
During design.
Before starting the
affected work.
After part of the work
has already been built.
The cost generally
increases at each stage.
During design, the
solution may involve changing a detail.
Before construction,
the project may alter the sequence or order a different product.
After installation,
the solution can involve demolition, rework and delay.
Developers often focus
on the cost of changing a design.
They should also
consider the cost of not changing it.
Rework Is More Than
Labour
The obvious cost of
rework is paying people twice.
There are other
effects.
Materials may be
wasted.
The next trade may be
delayed.
Site supervision is
diverted.
A quality inspection
may need to be repeated.
Updated information
must be communicated.
The project programme
loses contingency.
On a large commercial
project, one piece of rework is manageable.
Repeated rework
becomes a delivery problem.
Repetitive
Construction Needs More Buildability Review
The value of
buildability review increases when a detail is repeated.
This is particularly
relevant to hotels, retirement villages, apartment buildings and multi-unit
residential developments.
A small inefficiency
repeated hundreds of times becomes a substantial labour cost.
Savannah Construction
has experience across commercial and multi-unit carpentry packages where work
includes framing, linings, doors, ceilings and specialist construction details.
On these projects,
repetition can be an advantage.
Once a detail is
established, crews can become efficient.
The opposite is also
true.
A poor detail can
create repeated disruption.
Review the First
Installation Carefully
One practical method
is to treat the first installation as a benchmark.
Build the first room,
wall type, pelmet or repeated detail.
Review it.
Confirm the required
quality.
Check the sequence.
Identify missing
information.
Then repeat the
process.
This is more effective
than allowing five crews to interpret an unclear detail differently.
The principle is
simple.
Solve the problem
once.
Do not solve it 100
times.
Trade Interfaces
Create Buildability Risk
Many construction
problems occur between scopes.
The carpenter believes
the services contractor will provide framing.
The services
contractor believes the carpenter will provide it.
The fire contractor
expects an opening of a particular size.
The framing has
already been completed.
The door supplier
requires a finished opening that differs from the architectural plan.
No individual trade
necessarily made a major error.
The interface was not
managed.
Scope Coordination
Should Follow the Work
Large scope documents
are useful.
Site-specific
coordination is also required.
Before work reaches a
complicated area, the relevant trades should understand the sequence.
For example:
Who installs first?
What clearances are
required?
Who provides support?
What must remain
accessible?
What inspection is
required before closing the work?
Which drawing controls
the detail?
These are practical
construction questions.
A commercial
contractor should be willing to participate in these conversations before the
crew arrives in the area.
Programme Pressure
Can Hide Buildability Problems
When a project is
behind programme, the natural response is to add people.
Sometimes that works.
Sometimes it makes the
problem worse.
Twenty carpenters
cannot solve missing design information faster than ten carpenters.
More workers in a
restricted area can reduce productivity.
Multiple crews may
install the same unclear detail differently.
Before adding labour,
the project should identify the actual constraint.
Is the issue labour?
Access?
Information?
Material?
Sequence?
Inspection?
Another trade?
The solution should
match the problem.
Savannah Construction
operates with a substantial directly managed carpentry workforce supported by
off-site management.
For project managers,
the value of labour capacity is not simply the ability to put more workers on
site.
It is the ability to
allocate the right number of people to productive work.
Early Contractor
Input Does Not Need to Delay Design
Some developers assume
early contractor engagement means a long preconstruction process.
It does not have to.
A focused buildability
review can concentrate on high-risk areas.
Repeated details.
Complex interfaces.
High-labour elements.
Long-lead materials.
Difficult access.
Tight programme
stages.
The contractor does
not need to comment on every line of every drawing.
The objective is to
identify the parts of the scope most likely to affect delivery.
Ask Practical
Questions
Can the detail be
repeated consistently?
Is there room to
install it?
Does another trade
need access first?
Is temporary work
required?
Is the proposed
material readily available?
Can the area be
inspected before it is closed?
Does the programme
allow the required sequence?
These questions are
simple.
They often identify
expensive issues.
Buildability Is a
Project Team Responsibility
No contractor sees
every problem.
No designer sees every
problem.
No project manager
sees every problem.
Strong commercial
projects use the experience of the wider team.
The architect should
understand the design intent.
The engineer should
understand structural requirements.
The quantity surveyor
should understand cost.
The contractor should
understand physical delivery.
When these
perspectives are combined early, the project has better information.
That does not
guarantee a problem-free build.
Construction is too
complex for that promise.
It does reduce
avoidable risk.
Choosing a
Commercial Construction Company in Waikato
Savannah Construction
works with main contractors, developers and project teams on commercial and
multi-unit construction projects.
Our practical
experience is in delivering physical construction packages with significant
labour, coordination and programme requirements.
When reviewing a
commercial construction company in Waikato, developers should consider whether
the contractor only prices drawings or actively understands how the work will
be built.
Buildability is not a
construction buzzword.
It is the difference
between a detail that works on paper and a detail that can be delivered
efficiently, repeatedly and to the required quality on site.